Syncrude reduces oil shipments from Mildred Lake site
原始发布日期: 2017-06-13 发布者:虫子字变大 字变小
Company lowers output and reveals cause of March 14 fire and explosion
A fire which broke out at a Syncrude upgrader north of Fort McMurray on March 14 halted production at the site. (Pete Potipcoe/Facebook) Syncrude has reduced shipments of synthetic crude oil from its Mildred Lake, Alta., oilsands upgrader due to ongoing maintenance after the facility was shut down following a March 14 explosion and fire. Suncor, the majority owner of Syncrude, said in May it was shipping 140,000 barrels per day from Mildred Lake, a number the company expected to rise as seasonal maintenance was completed at the plant. On Tuesday evening, however, the company revised its output to 130,000 barrels per day, citing an accelerated maintenance schedule.
The company also gave new details about the cause of the explosion and fire that burned for two days, seriously injured one worker and forced the facility to shut down. Suncor said the cause of the incident was "a split in a six-inch carbon steel line on a naphtha hydrotreater recycle circuit." The damage, the company said, was mostly isolated to a pipe rack next to the hydrotreater, which contained pipes, cables and electrical circuits. The Mildred Lake upgrader is located 40 kilometres north of Fort McMurray. |